Hospital project taking shape

A conceptual view of the proposed new intensive care unit at the Cranbrook Regional Hospital from 24th Avenue North.  - Courtesy Interior Health
A conceptual view of the proposed new intensive care unit at the Cranbrook Regional Hospital from 24th Avenue North.
— image credit: Courtesy Interior Health

Interior Health is providing a progress report on its multimillion dollar expansion at East Kootenay Regional Hospital in Cranbrook.

Work on the new intensive care unit (ICU) and an electrical upgrade for the entire hospital began in May, and is proceeding on schedule, Interior Health said in a statement released Friday, August 1.

"The installation of the building substructure is well underway and proceeding on schedule," reads the statement. "All footings for the new structure are now complete and the base walls are approximately 30 per cent complete.

"The majority of underground drainage and sewer connections are also now in place. The basement floor is scheduled to be completed in August, and the ground floor and roof structures will be done in the fall."

The $20 million project began in May and will continue until summer 2016.

The new ICU will add an 8,500 square foot building to East Kootenay Regional Hospital with six patient rooms. It will be located on the northeast corner of the hospital.

The addition will replace the ageing, cramped four-bed Intensive Care Unit (ICU) at the hospital. The size and design of the new ICU will provide better flow through the unit for physicians and staff and providing additional privacy. The enhanced care environment for patients will feature integrated family spaces and maximized natural light.

The project includes a significant electrical upgrade to the entire hospital. The electrical infrastructure will be located in the basement of the new addition.

Interior Health said that next month, contractors Lark Projects Ltd will begin to install temporary generators and utility feeds for the electrical upgrades.

New permanent generators will arrive in December.

Work will continue on site from approximately 7 a.m. to 9 p.m. throughout the summer.

Drivers in the area can expect interruptions to normal traffic patterns throughout construction, but Interior Health said the contractor is working to minimize the interruptions.

The new ICU and electrical upgrade is being funded jointly by the B.C. government ($11.93 million), the Kootenay East Regional Hospital District ($7.95 million), and the East Kootenay Foundation for Health ($120,000).

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Bank shears off in a flow of mud
 
Tips for the Elk Valley Outdoor Enthusiasts
 
Cyclists tout green crossing over ravine
Suspects sought in violent Surrey robbery
 
To a slain soldier
 
Kist resigns as Pacific NorthWest LNG president; Progress Energy CEO acting president
Shootout suspects receive different sentences
 
HOMEFINDER: Empty nesters look to downsize
 
School trustee candidate: Scott Kimler

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 24 edition online now. Browse the archives.